01-20-2015 Regular School Board Meeting
Agenda Item #40


Title
Croton Elementary School Relocatable Classroom - Final Change Order and Close-out

Discussion

On 6/10/2014 the School Board approved Canaveral Construction Company, Inc. to provide Design/Build Services to install two relocatable classrooms at Croton Elementary School under their Continuing Contract for Design/Build Services for Guaranteed Maximum Price (GMP) of $75,703.20.

The work has been completed.  Reconciliation of unspent Contingency requested by the District has resulted in a deductive Change Order in the amount of ($6,194.70).

Attachment: Croton Elementary School Relocatable Classroom - Final Change Order and Close-out



Recommendation

Approve Change Order #1 to Canaveral Construction Company, Inc. for the Additional Relocatable Classrooms at Croton Elementary School under their Continuing Contract for Design/Build Services decreasing their Guaranteed Maximum Price by ($6,194.70) to $69,508.50 with no change in contract time.

 



Meeting Date(s)
Consent w/o Information - 1/20/2015

Authority for Action
FS 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
13/14$48,293.34Yes37430913057007400681000
13/14$27,409.86Yes38930913057007400681000

Contact
Dane Theodore, Asst. Supt. Facilities Management Services, 633-1000x657


Attachment:  Croton Elementary School Relocatable Classroom - Final Change Order - Close-out.pdf