01-21-2014 Regular School Board Meeting
Agenda Item #34


Title
Rockledge High School - GMP for Relocation of Portables to McLarty Stadium

Discussion

Relocate Surplus Portables N-151 and N-179 from Palm Bay High School to McLarty Stadium to replace existing unsatisfactory Storage Portables scheduled to be demolished.   

Canaveral Construction Co. Inc. has submitted a Guaranteed Maximum Price (GMP) under their Continuing Contract for Design Build Services in the amount of $42,863.55 for the relocation of the portables. 

Funding for this project will be provided by Rockledge High School.  

School Board approval is required for Purchase Orders over $25,000.  In order to expedite the work, approval is requested as a consent item without previous information.

Attachment:  McLarty Portable Relocation GMP



Recommendation
Approve the Guaranteed Maximum Price (GMP) submitted by Canaveral Construction Co. Inc. under their Continuing Contract for Design Build Services in the amount of $42,863.55 to relocate Surplus Portables N-151 and N-179 from Palm Bay High School to McLarty Stadium.  

Meeting Date(s)
Consent w/o Information - 1/21/2014

Authority for Action
F.S. 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Other Sources

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
13-14$42,863.55Yes38910110079237400681000

Contact
Joseph A. Ranaldi AIA; Director, Planning & Project Management; 633-1000 Extension 446


Attachment:  McLarty Portable Relocation GMP.pdf