02-09-2016 Regular School Board Meeting
Agenda Item #38


Title
Jefferson Middle School Design Build Services Guaranteed Maximum Price Amendment - SALES SURTAX

Discussion

Jefferson Middle School is the sixth highest priority on the Sales Surtax Planned Project Priority List. The cooling tower was replaced in summer 2015 through the sales surtax funding. The scope of work for this project includes all the remaining facility renewal items on the Sales Surtax Funded Detail Report (Attachment F), the district school security items and the classroom technology infrastructure.

Jefferson Middle School is one of several projects that are being done through the design build contract methodology. The process starts with the development of a Design Criteria Package (DCP) which is then used as the basis for the request for proposals (RFP) from design build contractors. RFP #16-P-022-DR was issued for the package of Tropical Elementary School and Jefferson Middle School to reduce administrative time and cost while achieving some economies of scale from the selected design builder. Five (5) proposals were received and Heard Construction, Inc. was awarded the contract and preconstruction services at the October 27, 2015 Board meeting.

The design is 60% complete and Heard Construction, Inc. has submitted a Guaranteed Maximum Price (GMP) amendment in an amount not to exceed $3,694,881.18, of which $3,351,283.09 is funded through sales surtax. The GMP reflects some risk mitigation because the design is not complete and subcontractor bidding has not been done. However, because there are long lead times on some of the equipment, the GMP is being submitted now to allow these procurements to move forward to substantially construct the project in summer 2016.  Additional surtax budget in the amount of $100,000 is requested for project administration and permitting. This may also cover costs for commissioning, a new Code requirement that was not in place at the time the sales surtax estimates were developed.

The GMP reflects an additional investment of $243,598.09 in capital funds. This will allow the project to incorporate removal of asbestos containing material on insulated pipes above the drop ceilings throughout with replacement of the affected ceiling soffits, grid and tile.  This work is also being done in conjunction with the upgrade to a variable air volume (VAV) system, which provides for more precise temperature control, less energy consumption, reduced compressor wear and less fan noise. Additional capital budget of $5,000 is requested for permitting and administrative support for the capital portion of the project.

As the project moves forward actual costs will be allocated to the sales surtax group and category as appropriate, based on the attached worksheet.

Board approval is required for purchase orders over $50,000. Approval is requested without prior information in order to expedite the work.

 

 

 

 



Recommendation

Approve the total project budget in the amount of $3,699,881.18 for the Jefferson Middle School renewal project of which $3,451,283.09 will be funded through sales surtax and $248,598.09 will be funded through capital.

Approve the GMP price amendment to the design build services contract with Heard Construction, Inc. in the amount not to exceed $3,594,881.18 of which $3,351,283.09 will be funded through sales surtax and $243,598.09 will be funded through capital.



Meeting Date(s)
Consent w/o Information - 2/9/2016

Authority for Action
F.S. 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
15/16$3,351,283.09Yes39841115000007400681000
15/16$243,598.09Yes37341113059637400681000
15/16$100,000Yes39841115000007400686000
15/16$5,000Yes37341113059637400686000

Contact
Susan Hann, P.E., Director of Planning and Project Management 633-1000 ext. 446