02-24-2015 Special School Board Meeting
Agenda Item #29


Title
Sea Park Elementary School - Guaranteed Maximum Price for Concrete Repairs and Roof Replacement for Building 14 Pavilion

Discussion

The District's Permitting Office identified concrete spalling and roof issues that are not in compliance with SREF and safety standards. These issues were investigated by a structural engineering consultant, Droor & Associations, under the District's continuing contract. The consultant recommended concrete repair and installation of a new two ply roof system.

Canaveral Construction Company, Inc. has submitted a Guaranteed Maximum Price (GMP) for the construction under the District's continuing contract for construction management services for an amount not to exceed $78,632.00.

The total project budget for the construction, administration, permitting, inspections and contingency is estimated not to exceed $88,700.

Because the project is to correct code and safety deficiencies, it will ultimately be funded through the sales tax. However, because sales tax revenues have not yet been received, the project will be advance-funded through the FY 2014-15 Capital Budget for correction of code and safety deficiencies.

Board approval is required for a purchase order over $25,000. In order to expedite the work, approval is requested as a consent agenda item without prior information.

Attachment: Sea Park Elementary School Pavilion Repair Budget Worksheet and GMP. 

 



Recommendation

Approve the Sea Park Elementary Concrete Repairs and Roof Replacement for Building 14 Pavilion for a total construction project cost not to exceed $88,700.

Approve the Guaranteed Maximum Price (GMP) submitted by Canaveral Construction Company, Inc. under their continuing contract for construction management services for the Sea Park Elementary School Pavilion Concrete Repair and Roof Replacement Project for the amount not to exceed $78,632.00



Meeting Date(s)
Consent w/o Information - 2/24/2015

Authority for Action
Florida Statutes 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
14/15$88,700yes37560513156267400671000

Contact
Susan Hann, P.E., Director of Planning and Project Management 633-1000 x450