Golfview E.S. Minor Renovations Phase II - Project Complete

Discussion

The purpose of this agenda item is to close the agreement for Construction Management Services with Ruby Builders, Inc. for the Minor Renovations Phase II at Golfview Elementary School.

On 11-19-13 the School Board approved the Guaranteed Maximum Price (GMP) of Ruby Builders, Inc. under their Continuing Contract for Construction Management in the amount of $214,266.17.

The work has been completed.  Reconciliation of unspent Contingency requested by the District has resulted in a deductive Change Order in the amount of ($22,104.76).

Attachment: Golfview E.S. Minor Renovations - Change Order and Certificate of Substantial Completion

 



Recommendation
Approve Change Order #001 to Ruby Builders, Inc. for Minor Renovations Phase II at Golfview E.S. under their Continuing Contract for Construction Management Services decreasing their Guaranteed Maximum Price by ($22,104.76) for unspent line items to $192,162.11 with no change to the Contract Time.

Meeting Date(s)
Consent w/o Information - 4/8/2014

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Agenda Item will not Require the Expenditure of Funds

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program

Contact
Joseph A. Ranaldi AIA; Director Planning & Project Management; 633-1000, Extension 446


Attachment:  Golfview E.S. Minor Renovations - Change Order and Certificate of Substantial Completion.pdf