04-14-15 Regular School Board Meeting
Agenda Item #43


Title
Sabal Elementary School Chiller/Cooling Tower Replacement - Close Out Change Order #2

Discussion
On 4/08/2014 the School Board approved Ruby Builders, Inc. to provide construction management services to replace the HVAC chiller unit and pumps serving the entire campus at Sabal Elementary School under their Continuing Contract for Construction Management Services for a Guaranteed Maximum Price (GMP) in the amount of $394,297.60.

On 12/16/2014 the School Board approved  Change Order #1, which included the deduction for Owner Direct Purchase (ODP) in the amount of $116,235.36 and additional scope to replace air handler unit 4 in the amount of $11,532.26 for a net deductive change order of $104,701.10 and a net increase in contract time of 157 days. The net contract amount after Change Order #1 was $289,594.50.
 
The work has been completed. Reconciliation requested by the District has resulted in a credit for unspent contingency in the amount of $1,475.00.  The remaining $1,475.00 of the credit is a savings which will be returned to the Capital Fund to be used on future projects. Change Order #2 reflects the credit, resulting in a final contract amount of $288,119.50.

Because of the cost of construction is over $300,000.00, the Florida Department of Education (FDOE) requires the Superintendent to sign the Certificate of Final Inspection (OEF-209) following certification by the Engineer/Architect of Record and the Building Official.


Recommendation
Approve Change Order #2, Project Closeout and Release of Final Retainage to Ruby Builders, Inc. for the Sabal Elementary School Chiller/Cooling Tower Replacement decreasing the GMP by $1,475.00 to $288,119.50.  
 
Authorize the Superintendent to sign FDOE OEF Form 209 - Certificate of Final Inspection for the project.


Meeting Date(s)
Consent w/o Information - 4/14/2015

Authority for Action
FS 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
13/14($1,475.00)Yes33730713059637400681000

Contact

Susan Hann, P.E., Director of Planning and Project Management 633-1000 ext. 450




Attachment:  Sabal HVAC Chiller Final Change Order #002 150330.pdf