Kennedy Middle School HVAC Make-Up Air Unit Replacement - Close Out Change Order #1

Discussion

On 10/22/2013 the School Board approved Mid-State Mechanical, Inc. to provide MEP Design Build Services under their Continuing Contract for the HVAC make-up air unit replacement at Kennedy Middle School for a Guaranteed Maximum Price (GMP) in the amount of $295,976.00.

The work has been completed. The reconciliation requested by the District has resulted in a credit for Owner Direct Purchases (ODP) in the amount of $95,625.78. The ODP credit is an administrative change only because the material and equipment were purchased directly by the District for installation by the construction manager. The District-requested change in the HVAC controls required an increase in the contract amount of $1,703.00.



Recommendation
Approve Change Order #1, Project Close Out and Release of Final Retainage to Mid-State Mechanical, Inc. for the HVAC make-up air unit replacement at Kennedy Middle School. Change Order #1 decreases the contract sum by $93,922.78 to $202,053.22, but includes an increase in the project cost of $1,703.00, with no change in contract time.

Meeting Date(s)
Consent w/o Information - 4/14/2015

Authority for Action
F.S. 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
13/14$1,703.00yes37211013059637400681000

Contact
Susan Hann, P.E., Director of Planning and Project Management 633-1000 ext. 450