West Shore Jr./Sr. High School - Construction Management Services

Discussion

The project is the renovation of the serving line at West Shore Jr./Sr. High School to improve capacity. Canaveral Construction, Inc., has submitted a Guaranteed Maximum Price (GMP) in the amount not to exceed $478,977 under their continuing contract for construction management services based on a design provided by RZK Architects. Administration and permitting expenses are estimated at $10,000.

The project will be funded by Food Services unrestricted funds.

Board approval is required for a purchase order over $50,000.

 



Recommendation

Approve the total project budget for West Shore Jr./Sr. High School serving line renovation project of $488,977.

Approve the Guaranteed Maximum Price (GMP) submitted by Canaveral Construction Inc., under their continuing contract for construction management services in an amount not to exceed $478,977.



Meeting Date(s)
Consent w/o Information - 5/9/2017

Authority for Action
F.S. 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
16/17$478,977Yes38931413157257400681000
16/17$10,000Yes38931413157257400686000

Contact
Susan Hann, P.E., Director of Planning and Project Management 633-1000 ext. 446.