Structured Cabling Infrastructure Upgrade for Tropical Elementary School

Discussion

The Educational Technology Division recommends to utilize RFQ #0802/LH  and contract with Construction Management Associates, Inc.  for construction management services to install structured cabling systems at Tropical Elementary School.  RFQ #0802/LH - Continuing Contracts for Construction.



Recommendation

The Sunrise Standard Plan has identified Tropical Elementary School as a required structured cabling retrofit.  The renovation will upgrade the computer network and telephone infrastructure to support the Sunrise Standard initiative.  The total construction project budget will not exceed $359,873.00



Meeting Date(s)
Information - 5/26/2009
Consent after Information6/16/2009

Authority for Action
Board Policy #6320 Florida Statue #287.057

Involves Expenditure of Funds Directly in the Classroom
Partial

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
08/09$359,873.00Yes33840410059207400681000