07-22-2014 Regular School Board Meeting
Agenda Item #26


Title
Brevard Schools Foundation Store at Clearlake Education Center - Change Order No.1

Discussion

On 12-10-2013 the School Board approved Heard Construction, Inc. to provide Design/Build Services to convert the east side of building 9 into a School Supply Store for the Brevard Schools Foundation under their Continuing Contract for Design/Build Services at Clearlake Education Center for a Guaranteed Maximum Price (GMP) of $58,380.93.

The work has been completed.  Reconciliation of unspent Contingency requested by the District has resulted in a deductive Change Order in the amount of ($6,380.93).

Attachment: Change Order No.1 Clearlake Education Center 



Recommendation
Approve Change Order No.1 to Heard Construction, Inc. for the Brevard Schools Foundation School Supply Store at Clearlake Education Center under their Continuing Contract for Design/Build Services decreasing their Guaranteed Maximum Price by ($6,380.93) to $51,774.63 with no change to contract time.

Meeting Date(s)
Consent w/o Information - 7/22/2014

Authority for Action
F.S. 1001.42

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
13/14$70,000.00Yes37810313059637400681000

Contact
Joseph A. Ranaldi AIA; Director, Planning & Project Management; 633-1000x446