Titusville High School Stormwater Improvements Change Order #1

Discussion

On 3/12/2013 the School Board approved Heard Construction Inc. to provide Construction Management Services for the Titusville High School Stormwater Improvements under their Continuing Contract for Construction Management Services for a Guaranteed Maximum Price (GMP) in the amount of $74,092.89.

The work has been completed.  Reconciliation of unspent Contingency requested by the District has resulted in a deductive Change Order in the amount of ($4,611.45).

Attachment:  Change Order #1 Titusville HS Stormwater     



Recommendation
Approve Change Order #1 to Heard Construction Inc. for the Titusville High School Stormwater Improvements under their Continuing Contract for Construction Management Services decreasing their Guaranteed Maximum Price by ($4,611.45) to $69,481.44.

Meeting Date(s)
Consent w/o Information - 8/13/2013

Authority for Action
1001.42 FS

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Agenda Item will not Require the Expenditure of Funds

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program

Contact
Joseph A. Ranaldi AIA; Director, Planning & Project Management; 633-1000, Extension 446