Change Order #1 to Paving at South Parking at Plant Operations and Maintenance Rockledge

Discussion

On June 12, 2012, the School Board approved Kinley Corporation to provide Construction Management Services for Paving at South Parking under their Continuing Contract for Construction Management Services for a Guaranteed Maximum Price of $54,999.80.

During the course of this work, additional Building Code requirements have resulted in a Change Order in the amount of $3,391.10.

Funding will be provided from the FY2013 Safety to Life budget.

Per Policy 6340, the Superintendent has approved the Change Order in the name of the Board for the purpose of expediting the work in progress.  Such approval must be confirmed by the Board at the nest regular or special Board Meeting.

Attachment:  Plant Operations and Maintenance Rockledge Paving at South Parking Change Order #1



Recommendation
Approve Change Order #1 to Kinley Corporation's Continuing Contract for Construction Management Services for Paving at South Parking at Plant Operations and Maintenance Rockledge, increasing their Guaranteed Maximum Price by $3,391.10 to $58,390.90 and extending their Contract Time by twenty three (23) days to August 29, 2012.

Meeting Date(s)
Consent w/o Information - 8/14/2012

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
12/13$3,391.10Yes37395623156267400671000

Contact
Ken Klindt, Director, Planning & Project Management 633-1000 x446