Change Order #1 to ADA Modifications at Eau Gallie High School

Discussion

On 6/12/12, the School Board approved Canaveral Construction Company to provide design/build services for ADA modifications at Eau Gallie High School under their Continuing Contract for Design/Build Services for a Guaranteed Maximum Price of $53,616.20.

During the course of this work, unforeseen conditions, additional scope requested by the Owner and additional Building Code requirements have resulted in a Change Order in the amount of  $12,456.30.

Funding will be provided from FY2012 ADA and Repair at Failure project budgets. 

Per Policy 6340, the Superintendent has approved the Change Order in the name of the Board for the purpose of expediting the work in progress.  Such approval must be confirmed by the Board at the next regular or special Board Meeting.  

Attachment: Eau Gallie High School ADA Modifications Change Order #1



Recommendation
Approve Change Order #1 to Canaveral Construction Company's Continuing Contract for Design/Build Services for ADA modifications at Eau Gallie High School, increasing their Guaranteed Maximum Price by $12, 456.30 to $66,072.50 and extending their Contract Time by eleven (11) days to August 12, 2012.

Meeting Date(s)
Consent w/o Information - 8/14/2012

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
12$1,126.00Yes31130113153887400681000
12$11,330.30Yes37230113059637400681000

Contact
Ken Klindt, Director, Planning & Project Management  633-1000 x446