09-25-2012 Special School Board Meeting
Agenda Item #40


Title
Modification #1 to Shutter Grant Project - Central Middle School

Discussion

On 01/24/12, the School Board approved 2011-2012 State of Florida, Division of Emergency Management Subgrant Agreement for Shelter Retrofit at Central Middle School.

Modification #1 will extend the time line for completion from 11/30/12 to 05/31/13.

Attachment: Modification #1 to Shutter Grant Project - Central Middle School.pdf



Recommendation
Approve Modification #1 that will extend the time line for the 2011-2012 State of Florida, Division of Emergency Management Subgrant Agreement for Shelter Retrofit at Central Middle School from 11/30/12 to 05/31/13.

Meeting Date(s)
Information - 9/25/2012
Consent after Information10/9/2012

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Agenda Item will not Require the Expenditure of Funds

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program

Contact
Ken Klindt, Director, Planning & Project Management 633-1000 x446


Attachment:  Modification #1 to Shutter Grant Project - Central Middle School.pdf