Tropical ES Walkway Roof Replacement - Change Order No. 1

Discussion

On 05/28/2013 the School Board approved Heard Construction Inc. to provide Design/Build Services to replace a deteriorated walkway roof system under their Continuing Contract for Design/Build Services at Tropical ES for a Guaranteed Maximum Price (GMP) of $196,833.74.

The work has been completed.  Reconciliation of unspent Contingency requested by the District has resulted in a deductive Change Order in the amount of ($19,982.26).

Attachment:  Change Order #1 Tropical ES Walkway   



Recommendation
Approve Change Order No. 1 to Heard Construction Inc. for the Tropical ES Walkway Roof Replacement under their Continuing Contract for Design/Build Services decreasing their Guaranteed Maximum Price by ($19,982.26) to $176,851.48 with no change to Contract Time. 

Meeting Date(s)
Consent w/o Information - 10/8/2013

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Agenda Item will not Require the Expenditure of Funds

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program

Contact
Joseph A. Ranaldi AIA; Director, Planning & Project Management; 633-1000, Extension 446