10-28-2014 Special School Board Meeting
Agenda Item #36


Title
Johnson MS Kitchen Renovation - Final Close-Out and Change Order #1

Discussion

On 04/22/2014 the School Board approved Heard Construction, Inc. to provide Construction Management Services for the Johnson Middle School Kitchen Renovation under their Continuing Contract for Construction Management Services for a Guaranteed Maximum Price (GMP) of $336,463.89.

The work has been completed.  Reconciliation of unspent Contingency requested by the District has resulted in a deductive Change Order in the amount of ($22,102.13).

Attachment: Johnson MS Kitchen Renovation Final Close-out and Change Order



Recommendation
Approve Change Order #1 to Heard Construction, Inc. for the Johnson Middle School Kitchen Renovation under their Continuing Contract for Construction Management Services decreasing their Guaranteed Maximum Price by ($22,102.13) to $314,361.76 with no change to the Contract Time.

Meeting Date(s)
Consent w/o Information - 10/28/2014

Authority for Action
1001.42 FS

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
FY14$824,167.85Yes4109360TBD7600681000

Contact
Joseph A. Ranaldi AIA; Director, Planning & Project Management; 633-1000, Extension 446


Attachment:  Johnson M S Kitchen Renovation Final Close-out Change Order.pdf