Change Order #1 to Emergency Purchase Order for Relocatable Classrooms for Riviera Elementary School

Discussion

On 09/25/12, The School Board approved Heard Construction, Inc. to provide Design/Build Services to relocate two (2) surplus relocatable classrooms from Bayside High School to Riviera Elementary School for a Guaranteed Maximum Price (GMP) of $83,792.15.

 

The work was completed.  Reconciliation of unspent Contingency requested by the Owner has resulted in a deductive Change Order in the amount of ($3,183.30).

 

Attachments:  Change Order #1 to Emergency Purchase Order for Relocatable Classrooms for Riviera ES.pdf 

 



Recommendation

Approve Change Order #1 to Heard Construction, Inc. Continuing Contract for Design/Build Services, decreasing their Guaranteed Maximum Price by ($3,183.30) to $80,608.85 with no change to their Contract Time.



Meeting Date(s)
Consent w/o Information - 11/20/2012

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Agenda Item will not Require the Expenditure of Funds

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program

Contact
Ken Klindt, Director, Planning & Project Management 633-1000 x446


Attachment:  Change Order #1 to Emergency Purchase Order for Relocatable Classrooms for Riviera ES.pdf