11-20-2012 Organization of the Board with Oath and Regular School Board Meeting
Agenda Item #37


Title
Change Order #2 to Paving at South Parking at Plant Operations and Maintenance Rockledge

Discussion

On June 12, 2012, the School Board approved Kinley Corporation to provide Construction Management Services for Paving at South Parking at Plant Operations and Maintenance Rockledge under their Continuing Contract for Construction Management Services for a combined revised Guaranteed Maximum Price of $54,999.80.

During the course of this work, additional Building Code requirements resulted in Change Order #1 in the amount of $3,391.10 which was approved on 08/14/12.

The work was completed.  Reconciliation of unspent Contingency requested by the Owner has resulted in a deductive Change Order in the amount of ($7,102.83).

Attachment: Change Order #2 Paving at South Parking Lot at Plant Operations & Maintenance.pdf



Recommendation
Approve Change Order #2 to Kinley Corporations Continuing Contract for Construction Management Services, decreasing their Guaranteed Maximum Price by ($7,102.83) to $51,288.07 with no change to their Contract Time.

Meeting Date(s)
Consent w/o Information - 11/20/2012

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Agenda Item will not Require the Expenditure of Funds

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program

Contact
Ken Klindt, Director, Planning & Project Management 633-1000 x446


Attachment:  Change Order #2 Paving at South Parking Lot at Plant Operations & Maintenance.pdf