Melbourne Bus Compound Underground Fuel Tank Replacement Change Order # 1

Discussion

On 03/11/2014 the School Board approved Canaveral Construction Company, Inc. to provide Design/Build Services to replace the underground fuel storage tanks under their Continuing Contract for Design/Build Services at the Melbourne Bus Compound for a Guaranteed Maximum Price (GMP) of $420,799.00.

During the course of this work unforeseen conditions were encountered and additional scope was requested by the District which has resulted in a Change Order totaling $18,857.35.

Adequate funding has been identified in the FY2013-14 Capital Funds

Attachment: Melbourne Bus Compound Change Order #1



Recommendation
Approve Change Order #1 to Canaveral Construction Company, Inc. for the Melbourne Bus Compound Underground Fuel Tank Replacement under their Continuing Contract for Design/Build Services increasing their Guaranteed Maximum Price by $18,857.35 to $439,656.35 with an extension to their Contract Time of 180 days.

Meeting Date(s)
Consent w/o Information - 12/16/2014

Authority for Action
1001.42 F.S.

Involves Expenditure of Funds Directly in the Classroom
No

Source of Funding
Capital Projects

FY
Amount
Budgeted
Fund
Cost Center
Project
Function
Object
Program
13-14$18,857.35Yes37293423059637400681000